Filing Your Montana Construction Lien

Make Sure You Get Paid By Filing a Lien Who Can File: Anyone who contributes something to the improvement can file.  However, suppliers of suppliers cannot file as they are too distant from the project. What Can Be Claimed: Anything that can be proven as having added to the work of improvement can be claimed.  You can […]

Montana Priorities Favor Lienors – Montana Mechanics Lien Held Valid

Yesterday we posted a blog about the Nevada Supreme Court’s ruling on priority of Nevada Mechanics liens over mortgages in situations where a bank has actual knowledge that a contractor commenced work, but there is no “visible” work being performed on the property.  In that case, the Nevada court ruled that actual knowledge of work […]